Akwa Ibom State Assembly Urges Governor To Investigate Delays In 29km Road Project Completion

Published

 Expressing concern over the prolonged delay in finishing the 29-kilometer road that traverses Nsit Atai, Okobo, and Oron local government areas within Akwa Ibom State, the State House of Assembly has called upon Governor Umo Eno to initiate a comprehensive inquiry aimed at identifying the obstacles hindering the project’s progress.

Furthermore, the Assembly, consisting of 26 members under the leadership of Speaker Hon. Udeme Otong, has instructed its Works and Transport Committee to exercise its supervisory authority by conducting an on-site evaluation of the road initiative….CONTINUE READING

 

The committee is also directed to engage with the Ministry of Works and Fire Service, overseen by Commissioner Prof. Eno Ibanga.

Sources indicate that this Assembly resolution is a result of a motion brought forward during a plenary session by the Chief Whip of the Assembly, Rt. Hon. Effiong Johnson, who represents the Mbo State Constituency. Johnson, a representative of Oron origin, highlighted the issue of the road project remaining incomplete nearly 17 years after the contract’s award.

He recalled that the decision to construct the Nsit-Atai-Oron road arose after the closure of the traditional route to Oron through the Ituk Mbang-Ekpene Ukim-Ndon Ebom road. This change became necessary due to the construction of an airport on farmland owned by Nsit-Atai, Uruan, and Okobo LGAs.

The initial contract for this road project was granted during the tenure of former Governor Victor Attah, followed by a subsequent re-award under the leadership of Governor Godswill Akpabio in 2006. Later, during Udom Emmanuel’s administration, the contract was revoked after the initial contractor, Renaissance Construction Company (RCC), failed to commence work within 10 months of being awarded the contract.

The project was subsequently re-awarded to a different construction firm in 2021, with the intention of completing the road before the administration’s conclusion in 2023.

Unfortunately, the Mbo lawmaker expressed regret that the commendable intentions of the Udom Emmanuel administration to ensure the road’s timely completion could not be achieved.