DisCos Launch Restoration Process After Nationwide Power BlackoutPower Distribution Companies have initiated load recovery following the third collapse of the national grid this week. As of 2:30 p.m., the load across the DisCos increased to 450 megawatts (MW), while the National Grid’s target remains at 4,800 MW.

Here’s the latest update on the load allocations for the DisCos:

•Abuja DisCo: 80 MW

•Benin DisCo: 70 MW

•Eko DisCo: 70 MW

•Enugu DisCo: 0 MW

•Ibadan DisCo: 100 MW

•Ikeja DisCo: 130 MW

•Jos DisCo: 0 MW

•Kaduna DisCo: 0 MW

•Kano DisCo: 0 MW

•PHarcourt DisCo: 0 MW

•Yola DisCo: 0 MW

Total: 450 MW

The grid experienced its third collapse early Saturday morning, resulting in widespread blackouts across several states. Data from the Nigerian System Operator’s portal indicated an unprecedented zero MW recorded at 8:16 a.m. today. The national grid confirmed via its verified social media account that seven out of eleven electricity distribution companies received no load allocation.

However, Ndidi Mbah, spokesperson for the Transmission Company of Nigeria (TCN), later announced that power had been restored.

 

For more information on this article and other related posts from Bushradiogist, please join our WhatsApp channel by clicking this link https://whatsapp.com/channel/0029VaUumOODTkK7AZL1Fw3o. For advertisement inquiries only, kindly send a message to 090 1907 0863 on WhatsApp.

Author:
BushRadio

Comments

0 comments

    Join the discussion

    Use a display name or leave it blank to comment as Anonymous. Email is not required.